Fwiw, project confirmed behind schedule. Pretty sure we all knew this. Source A+.
This isn't exactly true, btw. Schedule included a "float", basically a buffer of extra days built into the schedule to account for unforeseen issues or weather. Those extra days have been used for various reasons, but the project is still on schedule. It is likely that extra float days will be created during periods of good weather where the project can get ahead of schedule.
Any info on video board and sound system upgrades coming for this football coming football season. Also status of the Limestone wall. Thanks CC
Sound system for this Fall is unlikely. Nobody really knows how the stadium will be acoustically with the new structure and 50K fans in there. There will be lots of sound studies done during the first few games to monitor how sound is bouncing around in there, then they can start designing a sound system that works. Possible I guess that something is installed in-season, but more likely will be a '14 thing.
Wall, videoboard etc are being studied. Videoboard is higher priority. Haven't heard a go/no-go on that stuff for '13.
Probable that south concourse will have some work done on it for '13.